|
Shifting Risk for Unknown Subsurface Site Conditions in State and Federal Site Conditions
by John D. Cromie and John T. Fojut
Risk for unknown
subsurface site conditions is shifted differently between the public owner and
the contractor depending upon whether the project is state or federally
funded. Additionally, aside from the
employment of disclaimer or differing site conditions clauses in state and
federal contracts respectively, who bears the risk for
unknown subsurface site conditions is contingent upon an exacting factual and
legal balance of considerations, to include the entirety of the contract and
the specific facts attendant to the project.
As the recent cases cited in the article illustrate, however, a
determination of shifting risk for unknown subsurface conditions is one that cannot
be made in a vacuum.
The New
Jersey
Practice
The general
practice in New Jersey
is to shift the risk for unknown subsurface site conditions from the owner –
the state – to the contractor. The
bidding and contracting documents for state projects typically include an
exculpation clause that precludes the contractor from recovering monetary
damages for claims of delay and extra work caused by unknown subsurface site conditions
encountered during the course of the project.
The rationale
for the state’s disclaimer of liability for unknown conditions is to prevent
the escalation of project costs through the paying of claims for delay and
extra work. The practice is premised on
the theory that by exculpating itself from damages resulting from unknown
subsurface conditions, the state “forces” the contractor to perform whatever
pre-bid investigation is necessary to become familiar with the site – both
surface and subsurface. For example, if
the contractor bids on a project for which it will assume the extra costs
associated with encountering unknown subsurface conditions, it is theorized
that the contractor has an economic incentive to thoroughly investigate the subsurface
in order to minimize its own exposure for the unknown.
A legitimate
question exists as to whether the state’s general practice truly results in
lower project costs. The practical
effect of the public owner’s exculpation of liability for unknown subsurface
conditions is the artificial inflation of bids to capture the contractors’
“contingency” costs for the existence of unknown conditions. Contractors bidding on state projects must factor
their exposure for the unknown into their bids, with the potential result being
escalated project costs.
The
New Jersey Department of Transportation Standard Specifications’ exculpation
clause is contained in Section 102.06:
It
is expressly understood and agreed that the department assumes no
responsibility whatsoever in respect to the sufficiency or accuracy of the
subsurface investigations, the records thereof or of the interpretations set
forth therein or made by the department in its use thereof other than as used
to establish a design for the project in its as-built condition. There is no warranty or guaranty either
express or implied, that the conditions indicated by such investigations or
records thereof are representative of those existing throughout such areas, or
any part thereof, or that unlooked-for developments may not occur, or that
materials other than or in proportions different from those indicated may not
be encountered.
This exculpation clause is
typical of the state’s practice in that it shifts the risk of unknown
subsurface site conditions from the public owner to the contractor.
The
Supreme Court of New Jersey addressed the issue of shifting risk for changed
conditions – or unknown subsurface site conditions – in the seminal case of P.T.
& L. Construction Company, Inc. v. State of New Jersey, Department of
Transportation, decided in 1987 and reported at 108 N.J. 539 (1987).
In P.T. &
L. Construction Company, the Court considered a contractor’s claim against
the state for damages resulting from changed conditions on a public roadway
project. The contractor had expected dry
site conditions, in part, based on language contained in the contracting
documents, but instead encountered unanticipated wet site conditions.
The contract in P.T.
& L. Construction Company contained a standard exculpatory clause
disclaiming the state’s responsibility for changed site conditions. The clause provided, in relevant part: “[t]he
Contractor agrees that he will make no claims against the State, if in carrying
out the Project he finds that the actual conditions encountered do not conform
to those indicated by said borings, test excavations and other subsurface
investigations.” The Court found that
the contractor could recover for damages resulting from the fact that the site
was generally wet as opposed to dry.
Importantly, though, the Court based its decision on the state’s
nondisclosure of material facts which amounted to a misrepresentation of the
site conditions. The Court stated, “had [the contractor’s] claim been premised only on its
conclusion that dry working conditions were implicit in the contract specifications,
recovery would have been precluded by the specific disclaimers of State
responsibility for site conditions.”
P.T. & L.
Construction Company, thus, stands for the proposition that when the state
owner makes false representations in the contract documents – positive
statements of fact about the character of the work to be performed – the state
owner will be liable to the contractor for claims of delay and extra work
notwithstanding the existence of an exculpatory clause. Further, concealment of information regarding
surface or subsurface site conditions are considered false representations of
fact. Still, a contractor’s inferences
drawn from contracting documents are not considered false representations on
the part of the state provided that the state’s disclaimer as to actual site
conditions is clear and unambiguous.
More recently in SMC Corporation v. New Jersey
Water Supply Authority, a New Jersey Appellate Division case reported at
334 N.J. Super. 429 (2000), the Court considered a contractor’s claim against
the state for damages resulting from unknown subsurface site conditions. The contractor claimed damages resulting from
the existence of a scour hole that prevented the construction of planned
cofferdams. The scour hole was not depicted
in the specifications and drawings.
The
contract in SMC Corporation contained a disclaimer of liability for
unknown subsurface site conditions as follows:
The
contractor acknowledges that he has satisfied himself as to the nature and
location of the work, the general and local conditions particularly those
bearing upon transportation, disposal, handling and storage of materials,
availability of labor, water, electric power, roads and uncertainties of
weather, floods or similar physical conditions at the site, the topography and
conditions on the ground, the character of equipment and facilities needed
preliminary to and during the execution of the work, and all other matters upon
which information is reasonably obtainable and which can in any way affect the
work or the cost thereof under this Contract.
The Contractor further acknowledges that he has satisfied himself as to
the character, quality and quantity of information regarding the above that is
reasonably ascertainable from an inspection of the site, including all
exploratory work done by the [New Jersey Water Supply] Authority or the
Engineer, as well as information contained in the Drawings and Specifications
forming part of this Contract. The Contractor
further acknowledges that he has satisfied himself as to the availability of
timber, stone, fill material, etc. both as to quality and quantity required to
execute the work. Any failure by the
Contractor to acquaint himself with all the available information will not
relieve him from responsibility for estimating properly the difficulty or cost
to successfully perform the work.
The
Contractor’s attention is drawn to the fact that As-Built Drawings of existing
work do not exist and some dimensions shown on the Contract Drawings have been
estimated. All dimensions shall be field
checked by the Contractor.
Additionally, the drawings
contained a notation stating that the “information shown on the existing
conditions of the culvert and adjacent areas are based on field inspections
performed [several years earlier], and other information available at the
time. Actual field conditions may vary
from that shown on the contract drawings.”
The
Court determined that the state made no false statements of fact in the
contract documents. Still, the Court
ruled for the contractor, finding that the state’s “exculpatory” clause (quoted
above) to be ambiguous with respect to the allocation of risk for unknown
subsurface conditions. The Court
determined that “where ambiguities exist they are to be taken most strongly
against the draftsman.” As such, the
state assumed the risk for unknown subsurface site conditions.
The
Court in SMC Corporation compared the disclaimer clause in this case
with the disclaimer clause contained in P.T. & L. Construction Company.
The Court determined that while the P.T.
& L. Construction Company clause was unambiguous in placing the risk
for the subsurface condition on the contractor, the clause in SMC
Corporation implied that conditions not known to the public owner or contractor
– conditions which are not “reasonably obtainable” or “ascertainable” may be
the basis of a claim for delay and extra work.
In sum, the disclaimer used by the state in SMC Corporation was
not as strong as that used in P.T. & L. Construction Company.
The Federal Practice
The federal
practice shifts the risk for unknown subsurface site conditions from the
contractor to the federal public owner.
The bidding and contracting documents for federal projects include a
differing site conditions clause that permits the contractor to recover
monetary damages for claims of delay and extra work caused by changed
conditions, such as unknown subsurface site conditions encountered during the
course of the project.
Again, as with
the state practice, the rationale for the federal practice is to prevent the
escalation of project costs. In the
context of federal contracts, however, the rationale of the practice is to
prevent the escalation of project costs by preventing the contractor’s
inclusion of “contingency” costs in its bid.
The federal
practice is premised on the theory that by assuming the risk for unknown
subsurface site conditions, the federal owner eliminates the contractor’s need
to artificially inflate its bid to cover for problems that may or may not be encountered
during the course of the project; the result being a lower bid, a lower project
cost, and the elimination of a windfall to the contractor. Moreover, should there exist problematic
subsurface site conditions, and both the contractor
and federal owner are in agreement as to the changed site conditions, then an
equitable adjustment is made to the contract price.
Section
36.502 of the Federal Acquisition Regulation requires the use of a “differing
site conditions” clause in most federal construction projects. A typical differing site conditions clause is
as follows:
(a) The Contractor shall promptly, and before the
conditions are disturbed, give a written notice to the Contracting Officer of
(1) subsurface or latent physical conditions at the site which differ
materially from those indicated in this contract, or (2) unknown physical
conditions at the site, of an unusual nature, which differ materially from
those ordinarily encountered and generally recognized as inhering in work of
the character provided for in the contract.
(b) The Contracting Officer shall investigate the
site conditions promptly after receiving the notice. If the conditions do materially so differ and
cause an increase or decrease in the Contractor’s cost of, or the time required
for, performing any part of the work under this contract, whether or not
changed as a result of the condition, an equitable adjustment shall be made
under this clause and the contract modified in writing accordingly.
(c) No request by the Contractor for an equitable
adjustment to the contract under this clause shall be allowed, unless the
Contractor has given the written notice required; provided, that the time
prescribed in (a) above for giving written notice may be extended by the
Contracting Officer.
(d) No request by the Contractor for an equitable
adjustment to the contract for differing site conditions shall be allowed if
made after final payment under the contract.
The above quoted differing site
conditions clause was contained in the Kiewit Construction Company
contract discussed below.
The United
States Court of Federal Claims addressed the issue of shifting risk for unknown
subsurface site conditions in Kiewit Construction Company v. The United
States, reported at 56 Fed.Cl. 414
(2003). In Kiewit Construction
Company, the Court considered a contractor’s claim against the federal
government for differing site conditions on a project involving the
construction of a lock and gate bay. The
contractor brought a claim against the government for damages resulting from
unexpected water encountered at the work site – a claim falling under the
parameters claim type (1) in paragraph (a) of the differing site conditions
clause. The contractor claimed that the
owner’s specifications represented five conditions that differed from actual
site conditions; and, that such differing site conditions resulted in extra,
unforeseeable costs to the contractor.
The contract
work called for the creation of a dewatering system. The contract provided “mandatory minimum performance
and design information” with respect to the dewatering system. In addition to the differing site conditions
clause, the contract contained a provision stating that the assumptions
underlying the minimum dewatering system “may or may not be completely valid,”
and that “it shall be the Contractor’s sole responsibility to control and pump
any water that may leak through the existing structures . . . for whatever
conditions that may exist.”
The Court in Kiewit
Construction Company held that for the contractor to prevail on this claim,
it must demonstrate by a preponderance of the evidence the following: (1) that
the contract “affirmatively represented” the subsurface conditions forming the
contractor’s claims; (2) that the contractor acted as a reasonably prudent
contractor in interpreting the contract; (3) that the contractor reasonably
relied upon the subsurface conditions identified in the contract; (4) that the
subsurface conditions differed “materially” from the subsurface conditions
identified in the contract; (5) that the subsurface conditions encountered were
“unforeseeable;” and, (6) that the contractor’s claimed extra costs are purely
the result of the materially different subsurface conditions.
The Court rejected
the contractor’s claim, noting that the contract listed “baseline assumptions”
regarding subsurface conditions, and not factual representations as to the
subsurface. Further, the Court noted the
contract’s numerous disclaimers regarding the minimum work, and the necessity
of the contractor to determine whether or not site conditions require
augmentation to the minimum work in order to effect
performance under the contract. The
Court found that these assumptions, and the accompanying disclaimers, put the
contractor on notice that the contractor may be required to augment the
“minimum prescribed” work if the actual subsurface site conditions differed
from the baseline assumptions. Thus,
according to the Court, the contractor’s claim was not properly a differing
site conditions claim at all because the contract did not reference actual
conditions at the work site.
Conclusion
Shifting risk
for subsurface site conditions differs between state and federal projects. The prudent public owner and contractor should
have a command not only of the differences between the exculpatory and
differing site conditions clauses utilized by state and federal owners
respectively, but in the subtle nuances presented by the balance of the
contract and the factual realities presented by the project.
Published in the “New Jersey Constructor.” Permission from the Associated General Contractors of NJ, Publisher.
|